HMW Project Achieves 1,000t LCE Contained Inventory as Lithium Chloride Production Journey on Track

by admin April 29, 2024
April 29, 2024
HMW Project Achieves 1,000t LCE Contained Inventory as Lithium Chloride Production Journey on Track

Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to provide a further update on the progress of construction activities at its 100% owned Hombre Muerto West (HMW) Phase 1 lithium brine project, with lithium chloride production expected in H1 2025. Galan continues its steady progress in advancing its low cost, high grade HMW project to production in a timely manner.

HMW Project Update

Pond 1 and 2 evaporation continues; approx 1,000t LCE contained inventoryPond 3 earthworks almost complete, liner installation at 60% and filling of pond 3 commenced; Pond 4 earthworks have commencedOverall project completion now at 33%, with pond construction 45% complete; project execution is advancing as plannedAligning with the physical progress of the project, capital expenditure also sits at 33% of the Phase 1 budgetOpportunities to reduce the Capex and Opex for HMW Phase 1 identified; engineering and procurement teams working to quantify these opportunities within the next two monthsLow all-in sustaining costs; HMW is expected to be in the 1st quartile of lithium industry’s cost curve with an initial reserve estimate of 40 yearsPhase 2 Operating cost to LiCl concentrate of $US3,510/t LCE equates to a low Li2O equivalent operating cost of SC6 (Spodumene Concentrate) $US310/t-$US350/t; solid production margins at current spot prices

Overall completion of the HMW project now sits at 33% with the ponds system already at 45% completion. Approximately 600,000 m2 of evaporation area has now been built, currently housing 1,000t LCE contained inventory. This evaporation area is sufficient to produce a lithium chloride volume of approximately 2.4 ktpa LCE. The key processing parameters, including raw brine well average flow rates, Li grades and evaporation rates are all aligned with the Phase 1 DFS. Based on the rate of construction and the results achieved to date, the HMW project remains on track to start production in H1 2025.

In addition, Galan’s team are analysing options to reduce capital expenditure, these opportunities are focussed on selecting the minimum infrastructure required to commence production of Phase 1. Multiple trade-off exercises are being assessed such as the analysis of rental options for energy supply, reduction of the size for selected buildings, usage of independent smaller control systems, instead of a larger central control system for all facilities.

As previously announced, the HMW project was separated into four production phases. The initial Phase 1 Definitive Feasibility Study (DFS) focused on the production of 5.4ktpa LCE of a lithium chloride concentrate by H1 2025, as governed by the approved production permits. The Phase 2 DFS targets 21ktpa LCE of a lithium chloride concentrate in 2026, followed by Phase 3 production of 40ktpa LCE by 2028 and finally a Phase 4 production target of 60ktpa LCE by 2030. Phase 4 will include lithium brine sourced from both HMW and Galan’s other 100% owned project in Argentina, Candelas. The very positive Phase 2 DFS results were announced on 3 October 2023 (https://wcsecure.weblink.com.au/pdf/GLN/02720109.pdf).

Galan’s Managing Director, Juan Pablo (JP) Vargas de la Vega, commented:

“We are very proud of the solid progress being made by the HMW Phase 1 construction team. With more than one third of the project completion now achieved, Galan is well on its way towards its targeted commencement of production in H1 2025. Galan would like to acknowledge and sincerely thank the Government of the Catamarca Province in Argentina for their continued support, evidenced by the recent agreement signed to commercialise lithium chloride concentrate from HMW. We are excited about the opportunities this agreement now presents to Galan’s future”

Click here for the full ASX Release

This post appeared first on investingnews.com

0
FacebookTwitterGoogle +Pinterest
previous post
Beyond Lithium and Its Exploration Team Recognized with Bernie Schnieders Discovery of the Year Award
next post
Fast Track Applications Submitted for the Reefton and Sams Creek Projects

You may also like

Coinbase Expands USDC Rewards to Canada

September 17, 2025

Q4 & 2025 Trading Update

January 11, 2026

Flynn Expands Key Gold Targets at Golden Ridge,...

January 14, 2025

Atlantic Lithium

July 25, 2024

xU3O8 Token Launches on Major Global Trading Venues:...

July 25, 2025

Rio Silver arranges $1.3M private placement

September 12, 2025

Trump Orders Security Probe on Rare Earths and...

April 23, 2025

Coelacanth Energy

June 21, 2025

Brixton Metals: Diversified Exposure to Copper, Gold and...

January 13, 2026

Silver Traders Seek Out China as Solar Demand...

May 31, 2024

    Become a VIP member by signing up for our newsletter. Enjoy exclusive content, early access to sales, and special offers just for you! As a VIP, you'll receive personalized updates, loyalty rewards, and invitations to private events. Elevate your experience and join our exclusive community today!


    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.

    Popular

    • 1

      Hong Kong plans to install thousands of surveillance cameras. Critics say it’s...

    • 2

      UN experts urge Thailand not to deport dozens of Uyghurs to China where they face ‘real risk of torture’

    • 3

      Trump has assembled a team of China hawks. How will Beijing respond?

    • 4

      China executes man who plowed car into crowds in deadliest attack in a decade

    • 5

      How Calvin Klein and Tommy Hilfiger got caught in Trump’s trade war with China

    Categories

    • Business (1,401)
    • Investing (4,827)
    • Science (615)
    • World (3,687)
    Footer Logo
    • Privacy Policy
    • Terms & Conditions

    Disclaimer: dailywashingtoninsider.com, its managers, its employees, and assigns (collectively “The Company”) do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice. The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.

    Copyright © 2026 dailywashingtoninsider.com | All Rights Reserved